Recently, many were wondering why the excavating at Emerald Park Condominiums in the Yonge/Sheppard area was moving at a snail's pace. Based on the pictures taken in September and October, it seemed that not much digging was taking place to make way for five levels that are to be built below-ground.

Image by jivey80 of Metropia, Pure Plaza and Bazis' Emerald Park Condos site in September 2011

Image by jivey80 of Metropia, Pure Plaza and Bazis' Emerald Park Condos site in September 2011

Emerald Park was seemingly running behind schedule for the December excavation deadline. Blame it on the permits. Forum member matted recently had a conversation with Michael Brothers, a foreman on the site, who said, "If you count the actual work days on the site, they are much farther along and had there been no permit delays, likely would have been getting to the bottom."  

Although all the permits and paperwork will be formalized by the end of January, the digging has been picking up over the past few weeks, as illustrated by the pictures below.

Image by jivey80 of Metropia, Pure Plaza and Bazis' Emerald Park Condos site in September 2011

Image by vx64 of Metropia, Pure Plaza and Bazis' Emerald Park Condos site

Image courtesy of Bazis of Emerald Park's excavation site taken from the Nestle building

To stay on the updates to the Emerald Park Condos, keep checking the project's Forum thread here.  For more detailed info, such as specs and renderings, be sure to take a look at our dataBase page linked below.  

Developed by Bazis International in partnership with Metropia and Plaza, the complex was designed by Roy Varacalli. This is one project we certainly can't wait to see rise. 